Our Work
Cogeco Peer 1 Barrie Data Center
Client: Cogeco Data Services Inc
Project Goals
Ehvert was selected to provide turn-key services to convert an existing industrial building into the office and computing facility for a new 10 MW Data Centre in Barrie, Ontario in four discrete phases.
After Ehvert’s successful completion of Phase 1 of Cogeco Peer 1’s flagship data centre in 2013, Ehvert was again engaged to manage, design and construct Phases 2 through 4. While expanding the facility during these phases, Phase 1 remained occupied and continued full operations with no disruptions due to the construction. The total capacity of the data centre is 6 MW of IT load.
In Phases 2 through 4, Ehvert designed and built 3 additional computer rooms with a combined IT load capacity of approximately 3.6MW. This work included the successful management, implementation and commissioning of all the associated architectural, electrical distribution, power generation, critical cooling, building automation, and security infrastructure. Ehvert also provided one year of operational support and maintenance.
Project Results
- Phases 2-4 were completed while maintaining 24/7 power, cooling and operations within the live environment of Phase 1 with the shared facility, including a winter roof replacement for Phase 1.
- Ehvert managed the planning, permit, design and construction process from start to finish.
- The procurement team negotiated, finalized and managed over 350 sub-contracts with over 100 unique vendors.
- 5D BIM allowed for schedule tracking and awareness of when to use multiple daily labour shifts, being mindful of both the schedule gains and any labour cost premiums.
- Worked with the client to allow for early move in to priority areas while maintaining overall schedule.
- Prepared, applied for and administered what we believe to be the largest single pay-out from the IESO Funding Program ($1.8M).
Works
University Data Center
Client: University Data Center Project Goals Ehvert was retained to design, build and manage the University Data Center ...
MTS Data Centre Facility
Client: MTS, OneCap Investments Project Goals To design, build and manage the construction of a new 6 MW Uptime Institute ...
Hydro Quebec
Client: Hydro-Québec Project Goals The world’s largest generator of hydro electricity, Hydro-Québec required a robust, flagship data centre to ...
Enterprise Borden Data Centre
Client: Shared Services Canada, Defence Construction Canada Project Goals To consolidate over 500 data centres, Shared Services Canada and ...
Shaw Data Centre
Client: Shaw Business Project Goals Shaw Business engaged Ehvert to design this data centre as an upgrade to an ...
Cogeco (Aptum’s) Downtown
Client: Quiettouch Inc (purch. by Cogeco Peer 1) Project Goals Ehvert was engaged to design, manage and construct a ...
Cogeco Peer 1 Barrie Data Center
Client: Cogeco Data Services Inc Project Goals Ehvert was selected to provide turn-key services to convert an existing industrial ...